2024 Q4
- Carried out excavation and lateral support works for Portal Ancillary Building construction
- Carried out preparation works for tunnel construction
- Carried out water mainlaying works
2024 Q3
- Carried out excavation and lateral support works for Portal Ancillary Building construction
- Carried out Cut & Cover Tunnel construction
- Carried out water mainlaying works
2024 Q2
- Carried out excavation and lateral support works for Cut-and-Cover Tunnel and Portal Ancillary Building construction
- Carried out water mainlaying works
2024 Q1
- Carried out excavation and lateral support works for Cut-and-Cover Tunnel and Portal Ancillary Building construction
- Carried out water mainlaying works
- Carried out ground investigation works at Lion Rock
2023 Q4
- Carried out excavation and lateral support works for Cut-and-Cover Tunnel and Portal Ancillary Building construction
- Carried out water mainlaying works
- Carried out ground investigation works at Lion Rock
2023 Q3
- Carried out excavation and lateral support works for Cut-and-Cover Tunnel and Portal Ancillary Building construction
- Carried out water mainlaying works
- Carried out boulder survey
2023 Q2
- Carried out utility detection works
- Carried out site formation works
- Carried out excavation and lateral support works for Cut-and-Cover Tunnel and Portal Ancillary Building construction
- Erection of temporary fencing and hoarding
- Participated in CIC Life First Event 2023
2023 Q1
- Carried out utility detection works
- Carried out site formation works
- Carried out excavation and lateral support works for Cut-and-Cover Tunnel and Portal Ancillary Building construction
- Erection of temporary fencing and hoarding