Content
1.2 Construction Works Programme
1.4 License, Notification and Permits
1.5 Brief Summary of EM&A
Requirements
2.2 Air Quality Monitoring Parameter, Frequency and Duration
2.3 Monitoring Equipment and Methodology and QA/ QC Procedure
3.2 Noise Monitoring Parameter, Frequency and Duration
3.3 Monitoring Equipment, Methodology and QA / QC Procedure
3.4 Maintenance and Calibration
5. environmental site inspection and audit
6. environmental non-compliance
6.2 Summary of Environmental Non-Compliance
6.3 Summary of Environmental Complaint
6.4 Summary of Environmental Summon and Successful Prosecution
7.1 Construction Works and Potential Environmental Issues in the
next Reporting Period
8. ConclUsion, Comments and recommendation
8.2 Comments and Recommendations
List of Tables
Table I Summary
of EM&A Activities in the Reporting Period
Table II Summary
of Exceedance in the Reporting Period
Table 1.1 Status
of the TTA Sections
Table 1.2 Status
of Environmental License, Notification and Permits
Table 1.3 Summary of Status of Submission under EP-602/2021
Table 2.1 Air
Quality Monitoring Stations for Construction Phase
Table 2.2 Impact
Air Quality Monitoring Parameter, Duration and Frequency
Table 2.3 Impact
Air Quality Monitoring Equipment
Table 2.4 Action
and Limit Levels for 1-hour TSP
Table 2.5 Summary
of Impact 1-hour TSP Monitoring Results
Table 2.6 Influencing
Factors at / near Air Quality Monitoring Stations
Table 3.1 Noise
Monitoring Stations during Construction Phase
Table 3.2 Construction
Noise Monitoring Parameter, Frequency and Duration
Table 3.3 Construction
Noise Monitoring Equipment
Table 3.4 Action
and Limit Levels for Construction Noise Monitoring
Table 3.5 Summary
of Construction Noise Monitoring Results
Table 3.6 Influencing
Factors at Noise Monitoring Stations
Table 4.1 Summary
of Waste Generated in the Reporting Period
Table
5.1 Summary of Site
Inspections Observations and Recommendations
List of Figure
Figure
1.1 Project Layout Plan
Figure
2.1 Air Quality Monitoring
Stations
Figure
3.1 Construction Noise
Monitoring Stations
List of Appendices
Appendix
A Master Construction Programme
for the Project
Appendix
B Project Organization Chart and
Key Personnel Contact
Appendix
C Event and Action Plans
Appendix
D Project Implementation Schedule
Appendix
E Air Quality and Noise Monitoring
Equipment Calibration Certification
Appendix
F Environmental Monitoring
Schedule
Appendix
G Air Quality Monitoring Results
and Graphical Presentation
Appendix
H Extract of Meteorological
Observations for Hong Kong (Kai Tak)
Appendix
I Noise Monitoring Results and
Graphical Presentation
Appendix
J Waste Generation in the
Reporting Month
Appendix
K Summary of Complaint,
Notification of Summons and Prosecution and Cumulative Complaint Log
EXECUTIVE SUMMARY
This is the 20th Monthly Environment
Monitoring and Audit (EM&A) Report for Relocation of Diamon Hill Fresh
Water and Salt Water Service Reservoirs to Caverns
(the Project). This report was prepared by Acuity Sustainability Consulting
Limited under Contract No. 21/WSD/21 (hereafter called “the Contract”). This report documents the findings of EM&A
works during the reporting period from 1 November to 30 November 2024.
Key Construction Works in the Reporting Period
A summary of construction activities undertaken during
the reporting period is presented below:
Portion 1
& 3:
·
Prepare
for Mined Tunnel Work Force and Machines
·
Within
shaft, install and remove some strutting
·
PAB Pipe
Pile Installation (∅355)
·
PAB
Excavation & Tie Back Installation
·
C/C Tunnel construction
·
Steel
work for raking strut
·
Pump
house E&M provision
·
Tunnel
Pre-support
Portion
5:
·
Open
trench main laying works
·
ELS for
Receiving Pit
·
Reinstatement
works
·
Backfilling
works
·
Trial Pit
Works
Environmental Monitoring and Audit Programme
The monthly EM&A programme was undertaken by the
Environmental Team in accordance with the EM&A Manual. A summary of the monitoring and audit
activities during the reporting period is presented below:
Table I Summary
of EM&A Activities in the Reporting Period
EM&A Activities |
Date |
1-hour TSP Monitoring |
4, 9, 15, 21 and 27 November 2024 |
Construction Noise Monitoring |
4, 15, 21 and 27 November 2024 |
Weekly Environmental Site Inspection |
1, 8, 13 22 and 29 November 2024 |
Breaches of Action and Limit Levels
A summary of the environmental monitoring exceedance
of the reporting period is tabulated in Table
II.
Table II Summary of Exceedance in the Reporting
Period
Environmental Monitoring |
Parameter |
No. of non-project related exceedances |
Total no. of non-project related
exceedances |
No. of exceedances related to the project |
Total no. of exceedances related to the
project |
||
AL |
LL |
AL |
LL |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
Noise |
Leq(30-min) |
0 |
0 |
0 |
0 |
0 |
0 |
Note:
1. AL
refers to Action Level and LL refers to Limit Level.
Air Quality
No exceedance of Action Level or Limit Level was
recorded for 1-hour TSP monitoring during the reporting period.
Construction Noise
No Action Level exceedance was recorded for
construction noise monitoring during the reporting period.
No Limit Level exceedance was recorded for
construction noise monitoring during the reporting period.
Complaint Log
No environmental complaint was received in the
reporting period.
Notification of Summons and Successful Prosecutions
No notification of summons or successful
prosecutions was received in the reporting period.
Reporting Change
There was no reporting change in the reporting
period.
Future Key Construction Activities
Key construction activities to be considered in the
next two months included:
Portion 1 & 3:
·
Prepare for Mined
Tunnel Work Force and Machines
·
Within shaft, install
and remove some strutting
·
Substation
Construction
·
PAB Excavation &
Tie Back Installation
·
C/C Tunnel
construction
·
Steel work for raking
strut
·
Pump house E&M
provision
·
Tunnel Pre-support
Portion 5:
·
Open trench main
laying works
·
ELS for Receiving Pit
·
Reinstatement works
·
Backfilling works
·
Trial Pit Works
Potential environmental impacts arising from the
above construction activities are mainly associated with construction dust,
construction noise, water pollution control, waste management and landscape and
visual.
1.1.1
The relocated Diamond Hill Fresh Water and Salt Water
Service Reservoirs (DHSRs) will be constructed in a series of caverns linked by
access tunnels and adits. The relocated Diamond Hill
Fresh Water Service Reservoirs (DHFWSR) and Diamond Hill Salt
Water Service Reservoirs (DHSWSR) will be compartmented while the
existing Diamond Hill Pumping Station (DHPS) will be split into two (2) pump
houses for fresh and salt water supply when relocated.
1.1.2
Ancillary facilities to be constructed near the tunnel portal may include
transformer room, switch room, emergency generator room, control room,
ventilation building, and pumping station control room, which will be
constructed in an above-ground building outside the tunnel.
1.1.3
The scope of the Project comprises the following:
a)
Construction of the relocated DHSRs and associated
pumping stations and water main laying works;
b)
Construction of tunnels, adits,
ventilation system and caverns for accommodating the relocated DHSRs and the
associated facilities;
c)
Terminating the operation of the existing DHSRs and
the associated facilities; and
d)
All other associated works that are incidental to
and necessary for the completion of the Project.
1.1.4
The major construction activities of the Project include earthworks,
drilling and blasting, construction of concrete structures, handling and
transportation of excavated materials, water mains laying, installation of
electrical and mechanical (E&M) equipment and material transportation. The operation of the existing DHSRs and the
associated facilities will be terminated after the completion of the testing
and commissioning of the relocated DHSRs. Under the Project, the existing DHSRs and
associated facilities will be retained after termination of the operation. The subsequent demolition works will be
carried out by other government departments/ project proponents.
1.1.5
The Project construction was commenced on 31 March 2023 and the
completion date for the construction works would be on 12 April 2027.
1.1.6
The Project is a Designated Project under Item Q.2, Part I of Schedule 2
of the Environmental Impact Assessment Ordinance, "Underground Rock
Caverns", which requires an environmental permit from the Environmental
Protection Department (EPD) for its construction and operation.
1.1.7
Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the
Director of EPD granted the Environmental Permits (EP-602/2021) to the Water
Supplies Department (WSD) for the Project.
1.1.8
Acuity Sustainability Consulting Limited (ASCL) is commissioned by Chun
Wo – Sinohydro Joint Venture to undertake the role of
Environmental Team under the Environmental Permit (EP) EP-602/2021, and to
carry out the EM&A programme in fulfilment of the EM&A Manual, and
other requirements stipulated in the associated EIA Report.
1.1.9
This is the 20th Monthly EM&A Report
summarizing the key findings of the construction phase EM&A programme from 1
November to 30 November 2024 (the reporting period) and is submitted to fulfil
the requirements under Condition 3.4 of EP-602/2021 and Section 13.3 of the
EM&A Manual of the Project.
1.2.1
The construction works of the Project was commenced on 31 March
2023. The construction works programme,
and the location of construction works of the Project are shown in Appendix A and Figure
1.1, respectively. A summary of construction activities
undertaken during the reporting period is presented below:
Portion 1
& 3:
·
Prepare
for Mined Tunnel Work Force and Machines
·
Within
shaft, install and remove some strutting
·
PAB Pipe
Pile Installation (∅355)
·
PAB
Excavation & Tie Back Installation
·
C/C Tunnel construction
·
Steel
work for raking strut
·
Pump
house E&M provision
·
Tunnel
Pre-support
Portion
5:
·
Open
trench main laying works
·
ELS for
Receiving Pit
·
Reinstatement
works
·
Backfilling
works
·
Trial Pit
Works
1.2.2
Table
1.1 summarise the
status of temporary traffic sections near the works sites.
Table
1.1 Status
of the Temporary Traffic Arrangement (TTA) Sections
Name of TTA |
Status |
Section 1 – Lion Rock Road |
Implemented |
Section 1 - Chuk Yuen Road
(Westbound) near Tin Ma Court |
Implemented |
Section 1 - Chuk Yuen Road
(Eastbound) near Tin Wang Court |
Implemented |
Section 2 - Chuk Yuen Road
near Pang Ching Court |
Implemented |
Section 2 – Chuk Yuen Road
near Pang Ching Court (eastbound) |
Implemented |
Section 2 - Chuk Yuen Road
near Chuk Yuen South Estate (westbound) |
Implemented |
Section
2 - Chuk Yuen Road near Chuk Yuen Estate Bus Terminus (westbound) |
Implemented |
Section
2 - Chuk Yuen Road near Chuk Yuen Estate Bus Terminus (eastbound) |
Implemented |
Section
3 - Chuk Yuen Road near Bus Terminus (eastbound) |
Implemented |
Section
3 - Chuk Yuen Road near Market (westbound) |
Implemented |
Section
3 - Shatin Pass Road Top |
Removed
|
Section
3 - Shatin Pass Road Middle |
Removed |
Section
3 - Tsz Wan Shan Road stage 3 |
Implemented |
Section
3 - Lung Fung Street (Combine TTA with CSCE) |
Implemented |
Section
3 – Sheung Fung Street |
Implemented |
1.3.1
Different parties with different levels of involvement in the Project
organization include:
·
Project Proponent: Water Supplies Department (WSD)
·
Supervisor/ Engineer’s Representative (ER): Binnies Hong Kong Limited
·
Contractor: Chun Wo - Sinohydro Joint Venture
·
Environmental Team (ET): Acuity Sustainability Consulting Limited
·
Independent Environmental Checker (IEC): Umwelt Consulting Limited
1.3.2
The key personnel contact names and telephone number are presented in Appendix B.
1.4.1
A summary of the relevant permit, licences, and/ or notifications on
environmental protection for this Project are presented in Table 1.2.
Table 1.2 Status of Environmental License,
Notifications and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From
|
Expired
On |
||
Environmental Permit |
|||
EP-602/2021 |
14/12/2021 |
- |
Valid |
Notification Pursuant to Section 3(1) of the Air Pollution Control
(Construction Dust) Regulation |
|||
Ref. No.: 487301 |
09/12/2022 |
- |
Valid |
Billing
Account for Disposal of Construction Waste |
|||
7046085 |
04/01/2023 |
- |
Valid |
Registration
of Chemical Waste Producer |
|||
WPN 5213-282-C4760-0 |
30/12/2022 |
- |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
|||
WT00043965-2023 |
31/05/2023 |
31/05/2028 |
Valid |
WT10002621-2023 |
08/04/2024 |
30/04/2029 |
Valid |
Construction
Noise Permit |
|||
GW-RE0823-24 |
17/07/2024 |
19/11/2024 |
To be renewed |
GW-RE1199-24 |
07/10/2024 |
05/04/2025 |
Valid |
GW-RE0982-24 |
02/11/2024 |
22/12/2024 |
Valid |
GW-RE1223-24 |
14/10/2024 |
27/03/2025 |
Valid |
GW-RE1448-24 |
20/11/2024 |
31/03/2025 |
Renewal of GW-RE0823-24 |
GW-RE1542-24 |
04/12/2024 |
03/06/2024 |
To be Valid (Replacement
of GW-RE1199-24) |
1.4.2
The submission status of the EP and the implementation status of the
mitigation measures stated in the EP had been reviewed, all submission were
submitted/ deposited to the Director of Environmental Protection (DEP) on
schedule, no non-compliance of EP conditions was recorded during the reporting
period. The summary of submission status
under Environmental Permit EP-602/2021 are summarized in Table 1.3.
Table 1.3 Summary of Status of Submission under
EP-602/2021
EP Condition |
Title of
Submission |
Submission
Status |
1.11 |
Commencement Date of
Construction |
Notified the DEP on 22 Feb 2023 |
2.9 |
Management Organization(s) |
Informed the DEP on 20 Feb 2023 |
2.10 |
Environmental Permit (EP)
Submission Schedule |
22 Feb 2022 (1st Submission) |
2.11 |
Construction Works
Schedule and Location Plan |
28 Feb 2023 (Deposited) |
2.12 |
Construction Noise
Management Plan (CNMP) |
·
28 Feb 2023 (1st submission) ·
The EPD’s comments were issued on 8 Mar 2023 ·
The revised CNMP was submitted to the EPD for comment on 31 Jul 2023. ·
The EPD issued further comments on 16 Aug 2023. ·
The CNMP was further revised, certified by the ET Leader, verified by
the IEC, and issued to the EPD on 22 Aug 2023. ·
The revised CNMP was submitted to the EPD for comment on 15 Sept 2023. ·
The EPD had no further comment on 5 Oct 2023. |
2.13 |
Waste Management Plan
(WMP) |
·
28 Feb 2023 (1st submission) ·
The EPD’s comments were issued on 3 Apr 2023. ·
The revised WMP was submitted to the EPD for comment on 26 July 2023. ·
The WMP was further updated and submitted to the EPD on 16 Aug 2023. ·
The EPD had no further comment on 19 Sep 2023. |
2.14 |
Landscape and Visual
Mitigation Plan (LVMP) |
·
28 Feb 2022 (1st Submission) ·
The EPD’s comments were issued on 29 Mar 2023. ·
The revised LVMP was certified by the ET Leader, verified by the IEC,
and issued to the EPD on 22 Aug 2023. ·
The EPD issued further comments on 11 Sep 2023. ·
The revised LVMP was certified by the ET Leader, verified by the IEC,
and issued to the EPD on 15 Jan 2024. ·
The EPD issued further comments on 31
Jan 2024. ·
The revised LVMP was certified by the ET Leader, verified by the IEC,
and issued to the EPD on 19 Apr 2024 ·
The EPD had no further comment on 29 Apr 2024. |
3.3 |
Baseline Monitoring Report |
·
17 Mar 2023 (1st Submission) ·
27 Apr 2023 (2nd Submission) · 1 June 2023 (3rd Submission) ·
13 July 2023 (Formal submission) ·
3 Aug 2023 (accepted by the EPD) |
3.4 |
Monthly EM&A Report (October 2024) |
8 November 2024 |
4.2 |
Dedicated Internet
Website |
2 May 2023 |
1.4.3
Following the EPD’s comments on the Baseline Monitoring
Report (Ref. No. BMR-3.1, dated 17 March 2023), updating of air quality and
noise monitoring locations were proposed, including cancellation of noise
monitoring station at Tower 1, Meridian Hill (NM-1), resumption of air quality and noise
monitoring stations at Block 6, Tsui Chuk Garden (i.e. DM-4 and NM-4) and
proposal of new noise monitoring locations at Wo Tin House, Shatin Pass
Estate
(NM-5) and Sheung Fung Street
Customs Staff Quarter (NM-6).
1.4.4
Additional baseline monitoring for air quality
monitoring station DM-4, and noise monitoring stations NM-4, NM-5 and NM-6 was
carried out between 2 May and 16 May 2023. The Baseline Monitoring Report was updated
with all baseline monitoring results included, certified by the ET Leader, and
verified by the IEC on 30 May 2023. The updated
Baseline Monitoring Report was submitted to the EPD on 1 June 2023. A minor comment was received from the EPD on 26
June 2023. Following the advice from the
EPD, the Report was formally submitted to the EPD on 13 July 2023 after
amendment. The Report was accepted by
the EPD on 3 August 2023.
Air Quality
1.5.1
In accordance with the EM&A Manual, the ET shall carry out impact monitoring
during construction phase of the project. For 1-hour Total Suspended Particulates (TSP)
monitoring, the sampling frequency of at least three times every six days
should be undertaken when the highest dust impact occurs.
1.5.2
Action and Limit Levels for the 1-hour TSP monitoring works are discussed
in Section
2.4. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix C shall be carried out.
1.5.3
The air quality mitigation measures
detailed in the EM&A Manual were recommended to be implemented during the
construction phase. The implementation
statuses of these measures are presented in Appendix D.
Noise Monitoring
1.5.4
Construction noise monitoring should be
carried out at the designated monitoring stations directly affected by the
construction works once every week after the commencement of construction.
During construction works, one set of Leq(30-min)
measurement at each station between 0700 and 1900 hours on normal weekdays
shall be taken. If construction works are extended to include works during the
period between 1900 and 0700 hours, additional weekly impact monitoring shall
be carried out during evening and night-time works.
1.5.5
Action and Limit Levels for the noise
monitoring are discussed in Section 3.5. Should non-compliance of the
criteria occur, action in accordance with the Event and Action Plan presented
in Appendix C shall be carried out.
1.5.6
The noise mitigation measures detailed in
the EM&A Manual are recommended to be implemented during the construction
phase. The implementation statuses of
these measures are presented in Appendix D.
Environmental Requirements in Contract Documents
1.5.7
According to Particular Specification
(PS), the Contractor shall undertake environmental protection measures
to reduce the environmental impacts arising from the execution of the works. The Contractor shall also observe and comply
with relevant environmental protection and pollution control ordinances. The Contractor shall design, construct,
operate and maintain pollution control measures to ensure compliance with the
contract provisions as well as the environmental ordinances and their regulations.
1.5.8
The Contractor shall also:
·
Implement air pollution and noise abatement practices as specified in PS;
·
Minimise generation of wastewater from the Site;
·
On-site sorting of Construction and Demolition (C&D) materials;
·
Establish a mechanism to record the quantities of C&D materials
generated each month, using the monthly summary “Waste Flow Table”;
·
Control the use of timbers;
·
Implement a trip ticket system (TTS) for tracking the removal of C&D
materials from the Site to the disposal grounds;
·
Prepare an Environmental Management Plan (EMP) in accordance with GS
Section 25 and PS for implementation on the Site to reduce environmental
nuisance and C&D materials arising from Works, throughout the construction period;
·
Arrange weekly environmental walk to inspect the Site, checking that the
environmental performance of the Site is satisfactory and in compliance with
the requirements under the contract and EMP; and
·
Carry out site specific induction training about environmental management
as well as safety for all staffs and workers, and provide toolbox talks for
workers on environmental nuisance abatement and waste management.
2.1.1
The air quality monitoring locations for impact monitoring during the
reporting period are listed in Table
2.1 and presented
in Figure
2.1.
Table
2.1 Air Quality Monitoring Stations for
Construction Phase
ID |
Description |
Coordinates |
|
Northing |
Easting |
||
DM-1 |
Tennis
Court near Tin Ma Court |
822705 |
837047 |
DM-2 |
Chun
Sing House, Tin Ma Court |
822673 |
837143 |
DM-3 |
Grace
Methodist Church Kindergarten |
822782 |
837227 |
DM-4 |
Block
6, Tsui Chuk Garden |
822926 |
837246 |
DM-4a (1) |
Road pavement near Wang King House, Tin Wang Court |
822854 |
837340 |
Notes:
1.
An additional air quality
monitoring station DM-4a was proposed by the ET and agreed by the ER, IEC and
EPD.
2.2.1
Table 2.2 summarized the monitoring
parameter, duration, and frequency of impact air quality monitoring.
Table 2.2 Impact
Air Quality Monitoring Parameter, Duration and Frequency
Parameter |
Frequency |
Duration |
1-hour TSP |
3 times every 6 days |
Throughout the
construction phase |
Proposal of Using Portable Direct Reading Dust Meter
2.3.1
Direct reading dust meters were used for measuring 1-hour TSP levels
during the impact air quality monitoring. According to Section 4.4.1 of the EM&A
Manual, the proposed use of direct reading dust meters was submitted to and
agreed by the IEC.
2.3.2
Sufficient number of monitoring instruments was prepared by the ET for
carrying out the impact monitoring. All
equipment and associated instrumentation were clearly labelled.
2.3.3
Wind
data were collected from the records of Hong Kong Observatory Kai Tak Wind
Station (22.30966N,
114.21336E), which is located at the south-eastern side of
runway of the former Kai Tak Airport about 4.5 km south-east from the project
site.
2.3.4
Equipment used in the impact air quality monitoring programme is
summarised in Table
2.3. Calibration certificates for the impact air
quality monitoring equipment are attached in Appendix E.
Table
2.3 Impact Air Quality Monitoring
Equipment
Equipment |
Brand and Model |
Serial No. |
Calibration Due Date |
Direct Reading Dust Meter |
Sibata LD-5R |
0Z4545 |
28/11/2024 |
882106 |
28/11/2024 |
||
942532 |
28/11/2024 |
Maintenance and Calibration
2.3.5
Direct reading dust meters have been calibrated against high volume samplers
(HVSs) annually. A 2-day, three 3-hour
measurement results per day from direct reading dust meters were taken to
compare with the sampling results from the HVSs. The correlation between the direct reading
dust meters and the HVSs were then concluded.
By accounting for the correlation factor, the direct reading dust meters
are considered to achieve comparable results as that of the HVSs.
2.3.6
The 1-hour TSP measurement follows the instruction provided in the
manufacturer's manual. Before initiating
a measurement, zeroing the portable dust meter was carried out to ensure the
accuracy of each measurement.
2.4.1
The action and limit levels were established in accordance with the
EM&A Manual. Table
2.4 presents the
action and limits levels for 1-hour TSP monitoring. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix C shall be carried out.
Table
2.4 Action and Limit Levels for 1-hour
TSP
Monitoring
Station |
Action
Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
300.1 |
500 |
DM-2 |
289.0 |
|
DM-3 |
289.7 |
|
DM-4 |
294.9 |
|
DM-4a |
291.6 |
2.5.1
The impact air quality monitoring was conducted on 4, 9, 15, 21 and 27 November 2024. The impact
air quality
monitoring schedule for the reporting period is shown in Appendix F.
2.5.2
The monitoring results and graphical presentation of impact air quality
monitoring are shown in Appendix
G. No action or limit levels exceedance was
recorded in the reporting period.
Table 2.5 Summary of Impact 1-hour TSP Monitoring
Results
Monitoring
Station |
TSP
Concentration, μg/m3 |
Action Level |
Limit Level |
||
Average |
Minimum |
Maximum |
|||
DM-1 |
59 |
56 |
62 |
300.1 |
500 |
DM-2 |
56 |
54 |
58 |
289.0 |
|
DM-3 |
37 |
35 |
38 |
289.7 |
|
DM-4 |
44 |
40 |
47 |
294.9 |
|
DM-4a |
37 |
35 |
40 |
291.6 |
2.5.3
During the impact air quality monitoring, the major dust sources at each
monitoring stations were summarized in Table 2.6.
Table 2.6 Influencing
Factors at/ near Air Quality Monitoring Stations
Monitoring
Stations |
Influencing
Factors |
DM-1 |
Not identified |
DM-2 |
Not identified |
DM-3 |
Not identified |
DM-4 |
Not identified |
DM-4a |
Not identified |
2.5.4
Weather conditions during impact monitoring are presented in Appendix G and extracts of wind data recorded at Kai Tak Wind
Station available from the Hong Kong Observatory are presented in Appendix H.
3.1.1
The monitoring locations for construction noise monitoring are listed in Table 3.1 and shown in Figure 3.1.
Table 3.1 Noise Monitoring Stations during Construction
Phase
ID |
Description |
Measurement |
Coordinates |
|
Northing |
Easting |
|||
NM-2 |
Chun
Sing House, Tin Ma Court |
Façade |
822668 |
837143 |
NM-3 |
Grace
Methodist Church Kindergarten |
Façade |
822782 |
837227 |
NM-4 |
Block
6, Tsui Chuk Garden |
Façade |
822926 |
837246 |
NM-4a (1) |
Road pavement near Wang King House, Tin Wang Court |
Free field |
822854 |
837340 |
NM-5 (2) |
Wo Tin House, Shatin Pass Estate |
Façade |
823360 |
838143 |
NM-6 (2) |
Sheung Fung Street Customs Staff Quarters |
Free field |
823134 |
838412 |
Notes:
The noise monitoring station proposed in the EM&A
Manual (NM-1) was not available for baseline and impact monitoring. Therefore, impact monitoring at NM-1 was
cancelled and agreed by the ER, IEC and EPD.
(1)
An additional noise monitoring station
NM-4a was proposed by the ET and agreed by the ER, IEC and EPD.
(2)
Main laying works near NM-5 and NM-6 were
commenced in early September 2023. Noise
monitoring at NM-5 and NM-6 was commenced on 7 September 2023.
3.2.1
Construction noise level was measured by the ET and measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq(30-min)
was adopted as the monitoring parameter for the construction noise
monitoring.
3.2.2
As supplementary information for data auditing, statistical results such
as L10 and L90 were also obtained for
reference.
3.2.3
Table
3.2 summarized the monitoring parameters, duration, and
frequency of construction noise monitoring.
Table 3.2 Construction Noise Monitoring Parameter,
Frequency and Duration
Parameters |
Time |
Frequency |
Duration |
Leq(30-min) |
0700 and 1900 hours on normal weekdays |
Once every week |
Throughout the
construction phase |
3.3.1
As referred to the technical memorandum (TM) issued under the NCO, sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications were used
for carrying out the construction noise monitoring.
3.3.2
Noise measurements were not made in fog, rain, wind with a steady speed
exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed was checked with a portable
wind speed meter capable of measuring the wind speed in m/s.
3.3.3
Sufficient number of noise measuring equipment and associated instrumentation was prepared by the Environmental
Team. All the equipment and associated
instrumentation were clearly labelled.
3.3.4
Wind
data were collected from the records of Hong Kong Observatory Kai Tak Wind
Station (22.30966N,
114.21336E), which is located at the south-eastern side of
runway of the former Kai Tak Airport about 4.5 km south-east from the project
site.
3.3.5
The monitoring procedures are as follows:
·
For façade measurement, the monitoring station was set at a point 1 m
from the exterior of the sensitive receiver building façade and set at a
position 1.2 m above the ground. For
free-field measurement, the monitoring station was set at a position 1.2 m above ground.
·
The battery condition was checked to
ensure good functioning of the meter.
·
Parameters such as frequency weighting,
the time weighting and the interval were set as follows:
·
Frequency weighting: A
·
Time weighting: Fast
·
Interval: 30
minutes (Leq(30-min))
would be determined for daytime
noise
by calculating the logarithmic average of six consecutive Leq(5-min)
data
·
Prior to and after each noise measurement, the meter was calibrated using
an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level
before and after measurement is more than 1.0 dB, the measurement was
considered invalid and repeat of noise measurement will be required after
re-calibration or repair of the equipment.
·
At the end of the monitoring period, the values of Leq,
L90 and L10 were recorded. In addition, noise sources were recorded on a
standard record sheet.
3.3.6
Table
3.3 summarized the
noise monitoring equipment used during the construction noise monitoring. Calibration certificates for the impact noise
monitoring equipment are attached in Appendix E.
Table 3.3 Construction
Noise Monitoring Equipment
Equipment |
Model (Serial Number) |
Calibration Due Date |
Sound Level Meter |
NTi-XL2 (A2A-09696-E0) |
01/03/2025 |
Sound Calibrator |
Rion NC 74 (34615222) |
26/03/2025 |
3.4.1
Maintenance and calibration procedures are as follows:
·
The microphone head of the sound level meter and calibrator were regularly
cleaned with a soft cloth; and
·
The sound level meter and acoustic calibrator were calibrated annually by
a HOKLAS accredited laboratory or the manufacturer.
3.5.1
The Action and Limit Levels were established in accordance with the
EM&A Manual. Table
3.4 presents the
Action and Limit Levels for construction noise. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix C shall be carried out.
Table 3.4 Action and Limit Levels for Construction
Noise Monitoring
Monitoring
Stations |
Action Level |
Limit Level |
Time Period |
NM-2 |
When one documented complaint is received |
75 dB(A) |
0700 - 1900 hours on normal
weekdays |
NM-3 |
70/ 65 dB(A) * |
||
NM-4 |
75 dB(A) |
||
NM-4a |
75 dB(A) |
||
NM-5 |
75 dB(A) |
||
NM-6 |
75 dB(A) |
Notes:
If works
are to be carried out during restricted hours, the conditions stipulated in the
construction noise permit issued by the Noise Control Authority have to be followed.
* 70 dB(A) for school and 65 dB(A) during
school examination period.
3.6.1
The construction noise monitoring was conducted on 4, 15, 21 and 27 November 2024. The
monitoring schedule is presented in Appendix F.
3.6.2
The construction noise monitoring results are summarized in Table 3.5. No Action
Level or Limit Level exceedance was recorded in the reporting period. Details of the results and graphical
presentation are shown in Appendix
I.
Table 3.5 Summary of Construction Noise Monitoring
Results
Monitoring Station |
Noise Level, dB(A) |
Limit Level |
||
Leq(30-min) |
||||
Mean |
Minimum |
Maximum |
|
|
NM-2 |
71.8 |
70.9 |
72.2 |
75 dB(A) |
NM-3 |
58.2 |
58.0 |
58.4 |
70/ 65 dB(A) (1) |
NM-4 |
54.3 |
54.1 |
54.8 |
75 dB(A) |
NM-4a |
59.2 |
72.8 |
74.3 |
75 dB(A) |
NM-5 (2) |
55.1 |
68.5 |
69.0 |
75 dB(A) |
NM-6 (2) |
70.5 |
69.9 |
71.0 |
75 dB(A) |
Note:
(1)
70 dB(A) for
school and 65 dB(A) during school examination period.
(2)
Impact
monitoring at NM-5 and NM-6 was commenced on 7 September 2023.
3.6.3
Weather conditions during impact monitoring are presented in Appendix I and extracts of wind data recorded at Kai Tak Wind
Station available from the Hong Kong Observatory are presented in Appendix H.
3.6.4
During the construction noise monitoring period, the influencing factors
which may affect the results are summarized in Table 3.6.
Table 3.6 Influencing
Factors at Noise Monitoring Stations
Monitoring
Stations |
Influencing
Factors |
NM-2 |
Road traffic noise, construction
noise from 76 Broadcast Drive project |
NM-3 |
Road traffic noise |
NM-4 |
Road traffic noise |
NM-4a |
Road traffic noise |
NM-5 |
Road traffic noise |
NM-6 |
Road traffic noise |
4.1.1
Waste generated from the Project includes inert construction and
demolition (C&D) materials and non-inert C&D wastes in the reporting
period. The amount of waste generated by
the construction works of the Project during the reporting period is shown in Table 4.1 and the cumulative waste flow table was presented
in Appendix
J.
Table
4.1 Summary of Waste Generated in the
Reporting Period
Month |
Actual Quantalities of Inert C&D
Materials Generated Monthly |
Actual Quantities of C&D Wastes
Generated Monthly |
Actual Quantities of C&D Wastes
Recycled |
|||||||||||||
Total Quantity Generated |
Broken Concrete (including rock for recycling into
aggregates) |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper/ Cardboard Packaging |
Plastics |
Chemical Waste |
Others e.g., general refuse |
Metals |
Paper/ cardboard packaging |
Plastics (bottles/ containers, plastic
sheets/foam package material) |
Yard Waste |
Others |
|
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000m3) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000m3) |
|
November 2024 |
1.7171 |
0.00000 |
0.1556 |
0.7403 |
0.8212 |
0.0000 |
0.0000 |
0.0000 |
0.0000 |
0.0000 |
0.0177 |
0.0015 |
0.0033 |
0.0003 |
0.00000 |
0.00000 |
4.1.2
Construction and demolition (C&D) materials sorting was carried out
on site. Sufficient receptacles were
provided for general refuse collection and sorting. Excavated inert C&D materials were reused
to minimize the disposal of C&D waste to public fill.
4.1.3
The Contractor was advised to minimize the amount of waste through
recycling or reusing. All applicable
mitigation measures stipulated in the EM&A Manual and waste management
plans shall be fully implemented.
5.1.1
Site inspections were carried out by the
ET on a weekly basis to monitor the implementation of proper environmental
pollution control mitigation measures for the
Project. During the reporting period,
site inspections were carried out on1, 8, 13, 22 and 29
November 2024. A joint site inspection
with the ER, the Contractor and the IEC was carried out on 13 November 2024
5.1.2
During the site inspections in the
reporting period, no non-conformance was identified. Key observations and reminders during the site
inspections are described in Table 5.1.
Table
5.1 Summary of Site Inspection
Observations and Recommendations
Inspection Date |
Key Observations/ Reminders |
Follow-up Action |
1
November 2024 |
No
major environmental deficiency was observed. |
N/A |
8 November
2024 |
Portion
3 1.
Rock breaking process should take
measures to minimize dust dispersion |
Water has been sprayed. (Closed on 11 November 2024) |
13
November 2024 |
No
major environmental deficiency was observed. |
N/A |
22
November 2024 |
No
major environmental deficiency was observed. |
N/A |
29
November 2024 |
Work
area at Sheung Fung Street 1. The chemicals materials at site should be
labelled and equipped with trip tray to avoid land contamination 2. The noise barrier should be covering the
whole construction area to reduce noise generated from noisy works 1.
|
Removed. (Closed
on 29 November 2024) Covered
with noise barrier. (Closed
on 29 November 2024) |
5.1.3
According to the EIA Report, EP and the EM&A Manual, the mitigation
measures detailed in the documents are recommended to be implemented during the
construction phase. A summary of the
Project Implementation Schedule is provided in Appendix D.
6.1.1
No Action Level or Limit Level exceedance was recorded for 1-hour TSP
monitoring in the reporting period.
6.1.2
No Action Level or Limit Level exceedance was recorded for construction noise
monitoring in the reporting period.
6.1.3
Should the monitoring results of the
environmental monitoring parameters at any designated monitoring stations
indicate that the Action/ Limit Levels are exceeded, the actions in accordance
with the Event and Action Plans in Appendix C would be carried out.
6.2.1
No environmental non-compliance was recorded in the reporting period.
6.3.1
No environmental complaint was received in the reporting period. The Cumulative Complaint Log is presented in Appendix K.
6.4.1
There was no successful environmental prosecution or notification of
summons received since the Project commencement. The Cumulative Log for environmental summon
and successful prosecution is presented in Appendix K.
7.1.1
The construction programme for the Project
for the next reporting period is presented in Appendix A.
7.1.2
Works to be undertaken in the next two
months are summarized below:
Portion 1 & 3:
·
Prepare for Mined
Tunnel Work Force and Machines
·
Within shaft, install
and remove some strutting
·
Substation
Construction
·
PAB Excavation &
Tie Back Installation
·
C/C Tunnel
construction
·
Steel work for raking
strut
·
Pump house E&M
provision
·
Tunnel Pre-support
Portion 5:
·
Open trench main
laying works
·
ELS for Receiving Pit
·
Reinstatement works
·
Backfilling works
·
Trial Pit Works
7.1.3
Potential environmental impacts arising
from the above construction activities are mainly associated with construction
dust impact, noise impact, water quality impact, waste management and landscape
and visual.
7.2.1
The key environmental mitigation measures
for the Project in the coming reporting period associated with the above
construction activities will include:
Dust
· Regular
watering to reduce dust emissions from the exposed site surface;
· Stockpile
of dusty materials shall be covered entirely by impervious sheeting;
· Provide
vehicles washing facilities at all site exits to wash
away any dusty materials from vehicle body;
· NRMM
Labels should be displayed on the applicable equipment on site by the Contractor;
· All
vehicle and plant should be cleaned before they leave a construction site.
Noise
· Only
well-maintained plant should be operated on-site, and plant should be
maintained regularly during the construction programme;
· Quality
Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
· No
effluent discharge would be allowed before the effluent discharge license is
acquired.
· Surface
run-off from construction sites should be discharged into dedicated discharge
point via adequately designed sand/ silt removal facilities;
· Channels/
earth bunds/ sandbags barriers should be provided on site to properly direct
stormwater to silt removal facilities;
· Silt
removal facilities, channels and manholes should be maintained, and the
deposited silt and grit should be removed regularly;
· Open
stockpiles of construction materials on sites should be covered with tarpaulin
or similar fabric during rainstorms;
· Perimeter
channels should be provided on site boundaries where necessary to intercept
stormwater run-off from outside the site so that it will not wash across the site;
· Bare
slope should be covered completely by using canvas to reduce muddy surface
runoff during typhoons and rainstorms.
Waste Management
· Provision
of sufficient waste disposal points and regular collection of waste;
· Regular
cleaning and maintenance programme for drainage system;
· Chemical
containers shall be stored with drip tray underneath;
· Storage,
handling, transport, and disposal of chemical waste should be arranged in
accordance with the Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes published by EPD, and collected by a licensed chemical waste
collector.
Ecology
· Minimize
loss of habitats and associated wildlife;
· Using
directional lighting to prevent excessive light spill into adjacent natural
habitat and disturbance to nocturnal fauna.
Landscape and
Visual
· Adequate
tree protection measures shall be provided for the trees to be retained on
site.
8.1.1
This is the 20th
Monthly EM&A Report presenting the EM&A works during the reporting
period from 1 November 2024 to 30 November 2024 in accordance with
the EM&A Manual.
8.1.2
No Action Level or Limit Level exceedance was
recorded for 1-hour TSP monitoring in the reporting period.
8.1.3
No Action Level or Limit Level exceedance was recorded for construction
noise monitoring in the reporting period.
8.1.4
Environmental site inspections
were conducted on 1, 8, 13, 22 and 29 November 2024 by the ET in the reporting period.
8.1.5
No environmental complaint was received in the
reporting period.
8.1.6
No notification of summons and prosecution was
received in the reporting period.
8.1.7
The ET will keep track on the construction works to
confirm compliance of environmental requirements and the proper implementation
of all necessary mitigation measures.
8.1.8
No change to the EM&A programme was made in
this reporting period.
8.2.1
The proposed mitigation measures were properly implemented and were
considered effective and efficient in pollution control.
8.2.2
The ET had no recommendation following the completion of EM&A in the
reporting period.