Content
1.2 Construction Works Programme
1.4 License, Notification and Permits
1.5 Brief Summary of EM&A
Requirements
2.2 Air Quality Monitoring Parameter, Frequency and Duration
2.3 Monitoring Equipment and Methodology and QA/ QC Procedure
3.2 Noise Monitoring Parameter, Frequency and Duration
3.3 Monitoring Equipment, Methodology and QA / QC Procedure
3.4 Maintenance and Calibration
5. environmental site
inspection and audit
6. environmental
non-compliance
6.2 Summary of Environmental Non-Compliance
6.3 Summary of Environmental Complaint
6.4 Summary of Environmental Summon and Successful Prosecution
7.1 Construction Works and Potential Environmental Issues in the
next Reporting Period
8. ConclUsion,
Comments and recommendation
8.2 Comments and Recommendations
List
of Tables
Table I Summary of EM&A Activities in the Reporting
Period
Table II Summary of Exceedance in the Reporting Period
Table 1.1 Status of Environmental License, Notification and
Permits
Table 1.2 Summary of Status of Submission under EP-602/2021
Table 2.1 Air Quality Monitoring Stations for Construction Phase
Table 2.2 Impact Air Quality Monitoring Parameter, Duration and Frequency
Table 2.3 Impact Air Quality Monitoring Equipment
Table 2.4 Action and Limit Levels for 1-hour TSP
Table 2.5 Summary of Impact 1-hour TSP Monitoring Results
Table 2.6 Influencing Factors at / near Air Quality Monitoring
Stations
Table 3.1 Noise Monitoring Stations during Construction Phase
Table 3.2 Construction Noise Monitoring Parameter, Frequency and
Duration
Table 3.3 Construction Noise Monitoring Equipment
Table 3.4 Action and Limit Levels for Construction Noise
Monitoring
Table 3.5 Summary of Construction Noise Monitoring Results
Table 3.6 Influencing Factors at
Noise Monitoring Stations
Table 4.1 Summary of Waste
Generated in the Reporting Period
Table 5.1 Summary
of Site Inspections Observation and Recommendations
List
of Figure
Figure 1.1 Project
Layout Plan
Figure 2.1 Air
Quality Monitoring Stations
Figure 3.1 Construction
Noise Monitoring Stations
List of Appendices
Appendix A Master
Construction Programme for the Project
Appendix B Project
Organization Chart and Key Personnel Contact
Appendix C Event
and Action Plans
Appendix D Project
Implementation Schedule
Appendix E Air
Quality and Noise Monitoring Equipment Calibration Certification
Appendix F Environmental
Monitoring Schedule
Appendix G Air
Quality Monitoring Results and Graphical Presentation
Appendix H Extract
of Meteorological Observations for Hong Kong (Kai Tak)
Appendix I Noise
Monitoring Results and Graphical Presentation
Appendix J Waste
Generation in the Reporting Month
Appendix K Summary
of Complaint, Notification of Summons and Prosecution and Cumulative Complaint
Log
This is the 3rd
Monthly Environment Monitoring and Audit (EM&A) Report for Relocation of
Diamon Hill Fresh Water and Salt Water Service
Reservoirs to Caverns (the Project). This report was prepared by Acuity
Sustainability Consulting Limited under Contract No. 21/WSD/21 (hereafter
called “the Contract”). This report
documents the findings of EM&A works during the reporting period from 1
June to 30 June 2023.
Key Construction Works in the
Reporting Period
A summary of construction
activities undertaken during the reporting period is presented below:
·
Boundary Survey;
·
Open trench for main laying and
main laying works;
·
Pipe jacking of trenchless;
·
Hoarding erection and site setup;
·
Trial pit excavation;
·
Formation of piling platform;
·
Pipe pilling for C/C tunnel ELS wall;
·
Civil construction works, e.g. water supply; and
·
Pre-construction condition
survey.
Environmental Monitoring and Audit
Programme
The monthly EM&A programme
was undertaken by the Environmental Team in accordance with the EM&A
Manual. A summary of the monitoring and audit activities during the reporting
period is presented below:
Table I Summary
of EM&A Activities in the Reporting Period
EM&A Activities |
Date |
1-hour TSP Monitoring |
1, 7, 13, 19, 24 and 29 June 2023 |
Construction Noise Monitoring |
1, 7, 13, 19 and 29 June 2023 |
Weekly Environmental Site Inspection |
2, 9, 14, 23 and 30 June 2023 |
Breaches of Action and Limit
Levels
A summary of the environmental monitoring
exceedance of the reporting period is tabulated in Table II.
Table II Summary
of Exceedance in the Reporting Period
Environmental Monitoring |
Parameter |
No. of non-project related
exceedances |
Total no. of non-project
related exceedances |
No. of exceedances related to the project |
Total no. of exceedances
related to the project |
||
AL |
LL |
AL |
LL |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
0 |
Noise |
Leq(30-min) |
0 |
0 |
0 |
0 |
0 |
0 |
Air Quality
No action or limit levels exceedance
was recorded for 1-hour TSP monitoring during the reporting period.
Construction Noise
No action or limit levels
exceedance was recorded for construction noise monitoring during the reporting
period.
Complaint Log
No environmental complaint was
received in the reporting period.
Notification of Summons and
Successful Prosecutions
No notification of summons or
successful prosecutions was received in the reporting period.
Reporting Change
There was no reporting change in
the reporting period.
Future Key Issues
Key issues to be considered in
the next three months included:
·
Boulder survey;
·
Open trench for mainlaying and Mainlaying;
·
Pipe Jacking of trenchless;
·
Hoarding erection and site setup;
·
Trial pit excavation;
·
Formation of piling platform at
Zone 1 and Zone 2;
·
Pipe piling for C/C tunnel ELS wall;
·
Civil construction works, e.g. water supply;
·
Pre-construction condition survey;
·
Site compound site up
·
ELS works in Portion 3; and
·
Canopy table installation in
Portion 3.
Potential environmental impacts
arising from the above construction activities are mainly associated with
construction dust, construction noise, water pollution control, waste
management and landscape and visual.
1.1.1
The relocated Diamond Hill Fresh
Water and Salt Water Service Reservoirs (DHSRs) will
be constructed in a series of caverns linked by access tunnels and adits. The relocated Diamond Hill Fresh Water Service
Reservoirs (DHFWSR) and Diamond Hill Salt Water
Service Reservoirs (DHSWSR) will be compartmented while the existing Diamond
Hill Pumping Station (DHPS) will be split into two (2) pump houses for fresh
and salt water supply when relocated.
1.1.2
Ancillary facilities to be
constructed near the tunnel portal may include transformer room, switch room,
emergency generator room, control room, ventilation building, and pumping
station control room, which will be constructed in an above-ground building
outside the tunnel.
1.1.3
The scope of the Project comprises the
following:
a)
Construction of the relocated DHSRs
and associated pumping stations and water main laying works;
b)
Construction of tunnels, adits, ventilation system and caverns for accommodating the
relocated DHSRs and the associated facilities;
c)
Terminating the operation of the
existing DHSRs and the associated facilities; and
d)
All other associated works that are
incidental to and necessary for the completion of the Project.
1.1.4
The major construction activities
of the Project include earthworks, drilling and blasting, construction of
concrete structures, handling and transportation of excavated materials, water
mains laying, installation of electrical and mechanical (E&M) equipment and
material transportation. The operation
of the existing DHSRs and the associated facilities will be terminated after
the completion of the testing and commissioning of the relocated DHSRs. Under the Project, the existing DHSRs and
associated facilities will be retained after termination of the operation. The subsequent demolition works will be
carried out by other government departments/ project proponents.
1.1.5
The Project construction was commenced
on 31 March 2023 and the completion date for the construction works would be on
12 April 2027.
1.1.6
The Project is a Designated Project
under Item Q.2, Part I of Schedule 2 of the Environmental Impact Assessment
Ordinance, "Underground Rock Caverns", which requires an
environmental permit from Environmental Protection Department for its
construction and operation.
1.1.7
Pursuant to the Environmental
Impact Assessment Ordinance (EIAO), the Director of Environmental Protection
Department (EPD) granted the Environmental Permits (EP-602/2021) to the Water
Supplies Department (WSD) for the Project.
1.1.8
Acuity Sustainability Consulting
Limited (ASCL) is commissioned by Chun Wo – Sinohydro
Joint Venture to undertake the role of Environmental Team under the
Environmental Permit (EP) EP-602/2021, and to carry out the EM&A programme
in fulfilment of the EM&A Manual, and other requirements stipulated in the
associated EIA Report.
1.1.9
This is the 3rd Monthly
EM&A Report summarizing the key findings of the construction phase EM&A
programme from 1 June to 30 June 2023 (the reporting period) and is submitted
to fulfil the requirements in Conditions 3.4 of EP-602/2021 and section 13.3 of
the EM&A Manual of the Project.
1.2.1
The construction works of the
Project was commenced on 31 March 2023. The
construction works programme, and the location of construction works of the
Project are shown in Appendix A
and Figure 1.1,
respectively. A summary of construction activities undertaken during the
reporting period is presented below:
·
Boundary Survey;
·
Open trench for main laying and
main laying works;
·
Pipe jacking of trenchless;
·
Hoarding erection and site setup;
·
Trial pit excavation;
·
Formation of piling platform;
·
Pipe pilling for C/C tunnel ELS wall;
·
Civil construction works, e.g. water supply; and
·
Pre-construction condition
survey.
1.3.1
Different parties with different
levels of involvement in the Project organization include:
·
Project Proponent: Water Supplies
Department (WSD)
·
Supervisor/Engineer’s
Representative (ER): Binnies Hong Kong Limited
·
Contractor: Chun Wo - Sinohydro Joint Venture
·
Environmental Team (ET): Acuity
Sustainability Consulting Limited
·
Independent Environmental Checker
(IEC): Umwelt Consulting Limited
1.3.2
The key personnel contact names and
telephone number are presented in Appendix B.
1.4.1
A summary of the relevant permit,
licences, and/ or notifications on environmental protection for this Project
are presented in Table 1.1.
Table
1.1 Status of Environmental License,
Notifications and Permits
Permit / License No. |
Valid Period |
Status |
|
From |
Expired On |
||
Environmental
Permit |
|||
EP-602/2021 |
14/12/2021 |
- |
Valid |
Notification Pursuant to Section 3(1) of the
Air Pollution Control (Construction Dust) Regulation |
|||
Ref. No.:
487301 |
09/12/2022 |
- |
Valid |
Billing Account for Disposal of Construction Waste |
|||
7046085 |
04/01/2023 |
- |
Valid |
Registration of Chemical Waste Producer |
|||
WPN
5213-282-C4760-0 |
30/12/2022 |
- |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
|||
WT00043965-2023 |
31/05/2023 |
31/05/2028 |
Valid |
1.4.2
The submission status of the EP and
the implementation status of the mitigation measures stated in the EP had been
reviewed, all submission were submitted/ deposited to the Director of
Environmental Protection (DEP) on schedule, no non-compliance of EP conditions
was recorded during the reporting period. The summary of submission status
under Environmental Permit EP-602/2021 are summarized in Table 1.2.
Table 1.2 Summary of
Status of Submission under EP-602/2021
EP Condition |
Title of Submission |
Submission Status |
1.11 |
Commencement Date of Construction |
Notified the DEP on 22 Feb 2023 |
2.9 |
Management Organization(s) |
Informed the DEP on 20 Feb 2023 |
2.10 |
Environmental Permit (EP) Submission Schedule |
22 Feb 2022 (1st Submission) |
2.11 |
Construction Works Schedule and Location Plan |
28 Feb 2023 (Deposited) |
2.12 |
Construction Noise Management Plan (CNMP) |
28 Feb 2023 (Deposited) (Comments were issued by the EPD on 8 Mar 2023 and the CNMP is being
revised.) |
2.13 |
Waste Management Plan (WMP) |
28 Feb 2023 (Deposited) (Comments were issued by the EPD on 3 Apr 2023 and the WMP is being
revised.) |
2.14 |
Landscape and Visual Mitigation Plan (LVMP) |
28 Feb 2022 (1st Submission) (Comment were issued by the EPD on 29 Mar 2023 and the LVMP is being
revised.) |
3.3 |
Baseline Monitoring Report |
17 Mar 2023 (1st Submission) 27 Apr 2023 (2nd Submission) 1 June
2023 (3rd Submission) |
3.4 |
Monthly
EM&A Report (Apr
2023) |
15 May 2023 |
3.4 |
Monthly
EM&A Report (May
2023) |
12 June 2023 |
4.2 |
Dedicated Internet Website |
2 May 2023 |
1.4.3
Following the EPD’s comments on the
Baseline Monitoring Report (Ref. No. BMR-3.1, dated 17 March 2023), updating of
air quality and noise monitoring locations were proposed, including
cancellation of noise monitoring station at Tower 1, Meridian Hill (NM-1),
resumption of air quality and noise monitoring stations at Block 6, Tsui Chuk
Garden (i.e. DM-4 and NM-4) and proposal of new noise monitoring locations at Wo Tin
House, Shatin Pass Estate
(NM-5) and Sheung Fung Street Customs Staff Quarter (NM-6).
1.4.4
Additional baseline monitoring for
air quality monitoring station DM-4, and noise monitoring stations NM-4, NM-5
and NM-6 was carried out between 2 May and 16 May 2023. The Baseline Monitoring
Report was updated with all baseline monitoring results included, certified by
the ET Leader, and verified by the IEC on 30 May 2023. The Baseline Monitoring
Report was submission to the EPD on 1 June 2023.
Air Quality
1.5.1
In accordance with the EM&A Manual, the ET shall
carry out impact monitoring during
construction phase of the project. For 1-hour Total Suspended
Particulates (TSP) monitoring, the sampling frequency of at least three times
every six days should be undertaken when the highest dust impact occurs.
1.5.2
Action and Limit Levels for the 1-hour TSP
monitoring works are discussed in Section 2.4. Should
non-compliance of the criteria occur, action in accordance with the Event and
Action Plan presented in Appendix C shall be carried out.
1.5.3
The air quality
mitigation measures detailed in the EM&A Manual were recommended to be
implemented during the construction phase.
The implementation statuses of these measures are presented in Appendix
D.
Noise Monitoring
1.5.4
Construction noise monitoring should be carried out
at the designated monitoring stations directly affected by the construction
works once every week after the commencement of construction. During
construction works, one set of Leq(30-min)
measurement at each station between 0700 and 1900 hours on normal weekdays
shall be taken. If construction works are extended to include works during the
period between 1900 and 0700 hours, additional weekly impact monitoring shall
be carried out during evening and night-time works.
1.5.5
Action and Limit Levels for the noise monitoring are
discussed in Section 3.5. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix
C
shall be carried out.
1.5.6
The noise mitigation measures
detailed in the EM&A Manual are recommended to be implemented during the
construction phase. The implementation
statuses of these measures are presented in Appendix D.
Environmental Requirements in Contract Documents
1.5.7
According to Particular Specification (PS),
the Contractor shall undertake environmental protection measures to reduce the
environmental impacts arising from the execution of the works. The Contractor shall also observe and comply
with relevant environmental protection and pollution control ordinances. The Contractor shall design, construct,
operate and maintain pollution control measures to ensure compliance with the
contract provisions as well as the environmental ordinances and their
regulations.
1.5.8
The Contractor shall also:
·
Implement air pollution and noise abatement
practices as specified in PS;
·
Minimise generation of wastewater from the Site;
·
On-site sorting of Construction and Demolition
(C&D) Materials;
·
Establish a mechanism to record the quantities of
C&D materials generated each month, using the monthly summary “Waste Flow
Table”;
·
Control the use of timbers;
·
Implement a trip ticket system (TTS) for tracking
the removal of C&D materials from the Site to the disposal grounds;
·
Prepare an Environmental Management Plan (EMP) in
accordance with GS Section 25 and PS for implementation on the Site to
reduce environmental nuisance and C&D materials arising from Works, throughout
the construction period;
·
Arrange weekly environmental walk to inspect the
Site, checking that the environmental performance of the Site is satisfactory
and in compliance with the requirements under the contract and EMP; and
·
Carry out site specific induction training about
environmental management as well as safety for all staffs and workers, and
provide toolbox talks for workers on environmental nuisance abatement and waste
management.
2.1.1
The air quality monitoring locations for impact
monitoring during the reporting period are listed in Table
2.1
and presented in Figure 2.1.
Table 2.1 Air Quality Monitoring Stations for
Construction Phase
ID |
Description |
Coordinates |
|
Northing |
Easting |
||
DM-1 |
Tennis Court near Tin Ma Court |
822705 |
837047 |
DM-2 |
Chun Sing House, Tin Ma Court |
822673 |
837143 |
DM-3 |
Grace Methodist Church Kindergarten |
822782 |
837227 |
DM-4 (1) |
Block 6, Tsui Chuk Garden |
822926 |
837246 |
DM-4a (2) |
Road pavement near Wang King
House, Tin Wang Court |
822854 |
837340 |
Notes:
1.
Following
the EPD’s comment on the Baseline Monitoring Report (Ref. No. BRM-3.1, dated 17
March 2023), air quality monitoring at DM-4 was resumed. Baseline monitoring for air quality monitoring
station DM-4 was then carried out between 2 May and 16 May 2023. Impact monitoring at DM-4 was commenced on 22
May 2023.
2.
An additional
air quality monitoring station DM-4a was proposed by the ET and agreed by the
ER, IEC and EPD.
2.2.1
Table 2.2
summarized the monitoring parameter, duration, and frequency of impact air
quality monitoring.
Table 2.2 Impact
Air Quality Monitoring Parameter, Duration and Frequency
Parameter |
Frequency |
Duration |
1-hour
TSP |
3 times every
6 days |
Throughout
the construction phase |
Proposal of Using Portable Direct Reading Dust Meter
2.3.1
Direct reading dust meters were used for measuring
1-hour TSP levels during the impact air quality monitoring. According to Section 4.4.1 of the EM&A
Manual, the proposed use of direct reading dust meters was submitted to and
agreed by the IEC.
2.3.2
Sufficient number of monitoring instruments were
prepared by the ET for carrying out the impact monitoring. All equipment and associated instrumentation
were clearly labelled.
2.3.3
Wind
data were collected from the records of Hong Kong Observatory Kai Tak Wind
Station (22.30966N, 114.21336E), which is located at the south-eastern side of
runway of the former Kai Tak Airport about 4.5 km south-east from the project
site.
2.3.4
Equipment used in the impact air quality monitoring
programme is summarised in Table 2.3. Calibration
certificates for the impact air quality monitoring equipment are attached in Appendix
E.
Table 2.3 Impact Air Quality
Monitoring Equipment
Equipment |
Brand and Model |
Serial No. |
Calibration Due Date |
Direct Reading Dust Meter |
Sibata LD-5R |
851820 |
15/10/2023 |
882109 |
15/10/2023 |
||
2Y6549 |
01/03/2024 |
||
PC-3A(E) |
JC-220710221 |
08/10/2023 |
Maintenance and Calibration
2.3.5
Direct reading dust meters have been calibrated
against high volume samplers (HVSs) annually.
A 2-day, three 3-hour measurement results per day from direct reading
dust meters were taken to compare with the sampling results from the HVSs. The correlation between the direct reading
dust meters and the HVSs were then concluded.
By accounting for the correlation factor, the direct reading dust meters
are considered to achieve comparable results as that of the HVSs.
2.3.6
The 1-hour TSP measurement follows the instruction
provided in the manufacturer's manual.
Before initiating a measurement, zeroing the portable dust meter was
carried out to ensure the accuracy of each measurement.
2.4.1
The action and limit levels were established in
accordance with the EM&A Manual. Table 2.4 presents the action and limits
levels for 1-hour TSP monitoring. Should
non-compliance of the criteria occur, action in accordance with the Event and
Action Plan presented in Appendix C shall be carried out.
Table 2.4 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action Level (µg/m3) |
Limit
Level (µg/m3) |
DM-1 |
300.1 |
500 |
DM-2 |
289.0 |
|
DM-3 |
289.7 |
|
DM-4 |
294.9 |
|
DM-4a |
291.6 |
2.5.1
The impact air quality monitoring was conducted on 1,
7, 13, 19, 24 and 29 June 2023. The
impact air quality monitoring schedule for the reporting period is shown in Appendix
F.
2.5.2
The monitoring results and graphical presentation of
impact air quality monitoring are shown in Appendix G. No action or limit levels exceedance was
recorded in the reporting period.
Table 2.5 Summary of Impact 1-hour TSP Monitoring
Results
Monitoring
Station |
TSP
Concentration, μg/m3 |
Action
Level |
Limit
Level |
||
Average |
Minimum |
Maximum |
|||
DM-1 |
63 |
51 |
73 |
300.1 |
500 |
DM-2 |
58 |
53 |
64 |
289.0 |
|
DM-3 |
56 |
41 |
66 |
289.7 |
|
DM-4 (1) |
55 |
49 |
62 |
294.9 |
|
DM-4a |
62 |
40 |
69 |
291.6 |
Remark:
(1) Impact
air quality monitoring at DM-4 was commenced on 22 May 2023.
2.5.3
During the impact air quality monitoring, the major
dust sources at each monitoring stations were summarized in Table
2.6.
Table 2.6 Influencing
Factors at / near Air Quality Monitoring Stations
Monitoring
Stations |
Influencing
Factors |
DM-1 |
Not
identified |
DM-2 |
Not
identified |
DM-3 |
Not
identified |
DM-4 |
Not identified |
DM-4a |
Not
identified |
2.5.4
Weather conditions during impact monitoring are
presented in Appendix G and extracts of wind data recorded at Kai Tak Wind
Station available from the Hong Kong Observatory are presented in Appendix
H.
3.1.1
The monitoring locations for construction
noise monitoring are listed in Table 3.1
and shown in Figure 3.1.
Table 3.1 Noise
Monitoring Stations during Construction Phase
ID |
Description |
Measurement |
Coordinates |
|
Northing |
Easting |
|||
NM-2 |
Chun Sing House, Tin Ma Court |
Façade |
822668 |
837143 |
NM-3 |
Grace Methodist Church Kindergarten |
Façade |
822782 |
837227 |
NM-4 (2) |
Block 6, Tsui Chuk Garden |
Façade |
822926 |
837246 |
NM-4a (1) |
Road pavement near Wang King
House, Tin Wang Court |
Free field |
822854 |
837340 |
NM-5 |
Wo
Tin House, Shatin Pass Estate |
Façade |
823360 |
838143 |
NM-6 |
Sheung
Fung Street Customs Staff Quarters |
Free field |
823134 |
838412 |
Notes:
The
noise monitoring station proposed in the EM&A Manual (NM-1) was not
available for baseline and impact monitoring. Therefore, impact monitoring at NM-1 was cancelled
and agreed by the ER, IEC and EPD.
(1) An additional noise monitoring station NM-4a
was proposed by the ET and agreed by the ER, IEC and EPD.
(2) Following the EPD’s
comment on the Baseline Monitoring Report (Ref. No. BRM-3.1, dated 17 March
2023), noise monitoring station was resumed at NM-4. Baseline monitoring for noise monitoring
station NM-4 was then carried out between 2 May and 16 May 2023. Impact monitoring at NM-4 was commenced on 22
May 2023.
3.1.2
No construction work was conducted within
300m radius of noise monitoring station NM-5 and NM-6. Thus, no construction
noise monitoring was carried out at these two noise monitoring stations in the
reporting period.
3.2.1
Construction noise level was measured by the ET and
measured in terms of the A-weighted equivalent continuous sound pressure level
(Leq). Leq(30-min)
was adopted as the monitoring parameter for the construction noise
monitoring.
3.2.2
As supplementary information for data auditing,
statistical results such as L10 and L90
were also obtained for reference.
3.2.3
Table 3.2 summarized the monitoring
parameters, duration, and frequency of construction noise monitoring.
Table
3.2 Construction Noise Monitoring
Parameter, Frequency and Duration
Parameters |
Time |
Frequency |
Duration |
Leq(30-min) |
0700 and 1900 hours on normal weekdays |
once every week |
Throughout
the construction phase |
3.3.1
As referred to the technical memorandum (TM) issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications were used for carrying out the construction noise monitoring.
3.3.2
Noise measurements were not made in fog, rain, wind
with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed was checked with a portable
wind speed meter capable of measuring the wind speed in m/s.
3.3.3
Sufficient numbers of noise measuring equipment and
associated instrumentation were prepared by the Environmental Team. All the equipment and associated
instrumentation were clearly labelled.
3.3.4
Wind
data were collected from the records of Hong Kong Observatory Kai Tak Wind
Station (22.30966N, 114.21336E), which is located at the south-eastern side of
runway of the former Kai Tak Airport about 4.5 km south-east from the project
site.
3.3.5
The monitoring procedures are as follows:
·
For façade measurement, the monitoring station was
set at a point 1 m from the exterior of the sensitive receivers building façade
and set at a position 1.2 m above the ground. For free-field measurement, the monitoring
station was set at a position
1.2 m above the ground.
·
The battery condition was
checked to ensure good functioning of the meter.
·
Parameters such as
frequency weighting, the time weighting and the interval were set as follows:
·
Frequency weighting: A
·
Time weighting : Fast
·
Interval : 30 minutes (Leq(30-min)) would be
determined for daytime noise by calculating the logarithmic
average of six Leq(5-min) data
·
Prior to and after each noise measurement, the meter
was calibrated using an acoustic calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level
before and after measurement is more than 1.0 dB, the measurement was
considered invalid and repeat of noise measurement will be required after
re-calibration or repair of the equipment.
·
At the end of the monitoring period, the values of Leq, L90 and L10
were recorded. In addition, noise
sources were recorded on a standard record sheet.
3.3.6
Table 3.3 summarized the noise monitoring equipment used
during the construction noise monitoring.
Calibration certificates for the impact noise monitoring equipment are
attached in Appendix E.
Table 3.3 Construction Noise
Monitoring Equipment
Equipment |
Model (Serial Number) |
Calibration Due Date |
Sound
Level Meter |
Nti-XL2
(A2A-13548-E0) |
05/02/2024 |
Sound
Calibrator |
Rion NC
75 (35124529) |
08/11/2023 |
3.4.1
Maintenance and calibration procedures are as
follows:
·
The microphone head of the sound level meter and
calibrator were regularly cleaned with a soft cloth; and
·
The sound level meter and acoustic calibrator were
calibrated annually by a HOKLAS accredited laboratory or the manufacturer.
3.5.1
The Action and Limit levels were established in
accordance with the EM&A Manual. Table 3.4 presents the Action and Limit
Levels for construction noise. Should non-compliance of the criteria occur,
action in accordance with the Event and Action Plan presented in Appendix
C
shall be carried out.
Table 3.4 Action and Limit Levels for Construction
Noise Monitoring
Monitoring Stations |
Action Level |
Limit Level |
Time Period |
NM-2 |
When one documented complaint is received |
75 dB(A) |
0700 - 1900 hours on normal weekdays |
NM-3 |
70/ 65 dB(A) * |
||
NM-4 |
75 dB(A) |
||
NM-4a |
75 dB(A) |
||
NM-5 |
75 dB(A) |
||
NM-6 |
75 dB(A) |
Notes:
If works are to be carried out during restricted hours, the conditions stipulated
in the construction noise permit issued by the Noise Control Authority have to be followed.
* Reduce to 70 dB(A) for schools
and 65 dB(A) during school examination periods.
3.6.1
The construction noise monitoring was conducted on 1,
7, 13, 19 and 29 June 2023. The monitoring schedule is presented in Appendix
F.
3.6.2
The construction noise monitoring results are
summarized in Table 3.5. No Action
or Limit levels exceedance was recorded in the reporting period. Details of the results and graphical
presentation are shown in Appendix I.
Table 3.5 Summary
of Construction Noise Monitoring Results
Monitoring
Station (1) |
Noise
Level, dB(A) |
Limit
Level |
||
Leq(30-min) |
||||
Mean |
Minimum |
Maximum |
|
|
NM-2 |
71.1 |
70.7 |
71.5 |
75 dB(A) |
NM-3 |
64.2 |
62.9 |
66.7 |
70/ 65 dB(A) (2) |
NM-4 (3) |
66.1 |
65.6 |
67.1 |
75 dB(A) |
NM-4a |
72.1 |
71.4 |
72.4 |
75 dB(A) |
Note:
(1)
Construction
noise monitoring at NM-4 and NM-5 will commence when construction works are
undertaking near these stations.
(2)
Reduce
to 70 dB(A) for schools and 65 dB(A) during school examination periods.
(3)
Impact
monitoring at NM-4 was commenced on 22 May 2023.
3.6.3
Weather conditions during impact monitoring are
presented in Appendix I and extracts of wind data recorded at Kai Tak Wind
Station available from the Hong Kong Observatory are presented in Appendix
H.
3.6.4
During the construction noise monitoring period, the
influencing factors which may affect the results are summarized in Table
3.6.
Table 3.6 Influencing Factors at Noise Monitoring
Stations
Monitoring
Stations |
Influencing
Factors |
NM-2 |
Road traffic
noise, construction noise from 76 Broadcast Drive project |
NM-3 |
Road
Traffic Noise |
NM-4 |
Road
Traffic Noise |
NM-4a |
Road
Traffic Noise |
4.1.1
Waste generated from the Project includes inert
construction and demolition (C&D) materials and non-inert C&D wastes in
the reporting period. The amount of waste generated by the construction works
of the Project during the reporting period is shown in Table
4.1
and the cumulative waste flow table was presented in Appendix
J.
Table 4.1 Summary of Waste Generated in the
Reporting Period
Month |
Actual Quantalities of
Inert C&D Materials Generated Monthly |
Actual Quantities of
C&D Wastes Generated Monthly |
Actual Quantities of
C&D Wastes Recycled |
|||||||||||||
Total Quantity
Generated |
Broken Concrete (Including rock for
recycling into aggregates) |
Reused in the Contract |
Reused in other
Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / Carboard
Packing |
Plastics |
Chemical Waste |
Others e.g., general
refuse |
Metals |
Paper/ cardboard
packaging |
Plastics (bottles/ containers,
plastic sheets/foam package material) |
Yard Waste |
Others |
|
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000m3) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000m3) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000m3) |
|
Jun 2023 |
0.14853 |
0.00000 |
0.00000 |
0.00000 |
0.14853 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
0.03804 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
0.00000 |
4.1.2
Construction and demolition (C&D) materials
sorting was carried out on site.
Sufficient receptacles were provided for general refuse collection and
sorting. Excavated inert C&D
materials were reused to minimize the disposal of C&D waste to public fill.
4.1.3
The Contractor was advised to minimize the amount of
waste through recycling or reusing. All
applicable mitigation measures stipulated in the EM&A Manual and waste
management plans shall be fully implemented.
5.1.1
Site inspections were
carried out by the ET on a weekly basis to monitor the implementation of proper
environmental pollution control mitigation measures for the Project. During the reporting period, site inspections
were carried out 2, 9, 14, 23 and 30 June 2023. Joint site inspection with the ER, the
Contractor and the IEC was carried out on 14 June 2023.
5.1.2
During the site
inspections in the reporting period, no non-conformance was identified. Key observations and reminders during the site
inspections are described in Table 5.1.
Table 5.1 Summary
of Site Inspection Observations and Recommendations
Inspection Date |
Key Observation / Reminders |
Follow-up Action |
2
June 2023 |
No major
environmental deficiency was observed. |
N/A |
9 June 2023 |
1.
Chemical containers should be stored with drop tray to prevent
oil leakage. (Observation) 2.
Storm drain should be covered to prevent site runoff
washing in. (Observation) 3.
The Contractor was reminded to place an impervious sheeting
underneath the drill to prevent land contamination. (Reminder) |
1.
Chemical containers were removed. 2.
Exposed earth surface was hard paved. 3.
The drill was removed. |
14 June 2023 |
1.
At the lower part of the Portion 3, sandbags should be
properly aligned the road kerb and the exposed ground and soil should be
properly covered by tarpaulin sheets to reduce silty runoff during rainfall.
(Observation) |
1.
Sandbags was properly aligned the road kerb, and the
exposed ground and soil was hard paved to reduce silty runoff. |
23 June 2023 |
1. Oil leakage from
the piling rig was observed, the Contractor was required to repair the piling
rig to prevent leakage. The removal works of contaminated soil should be
followed the guideline published by the EPD. (Observation) 2. The Contractor
should replace the NRMM Label on the piling machine in the site area.
(Reminder). 3. The Contractor
shall provide drip tray under the air compressor to prevent leakage. (Reminder) |
1. The piling rig
was repaired, and the contaminated soil was treated and disposed following
the guideline published by the EPD. 2. NRMM Label was
replaced. 3. Dip tray was
provided for air compressor. |
30 June 2023 |
1. The door of the
air compressor shall be closed. (Reminder) |
1. The door of the
air compressor was closed. |
5.1.3
According to the EIA
Report, EP and the EM&A Manual, the mitigation measures detailed in the
documents are recommended to be implemented during the construction phase. A summary of the Project Implementation
Schedule is provided in Appendix D.
6.1.1
No Action Level or Limit Level exceedance was
recorded for 1-hour TSP monitoring in the reporting period.
6.1.2
No Action Level or Limit Level exceedance was
recorded for construction noise monitoring in the reporting period.
6.1.3
Should the monitoring
results of the environmental monitoring parameters at any designated monitoring
stations indicate that the Action/ Limit Levels are exceeded, the actions in
accordance with the Event and Action Plans in Appendix C would be
carried out.
6.2.1
No environmental non-compliance was recorded in the
reporting period.
6.3.1
No environmental complaint was received in the
reporting period. The Cumulative
Complaint Log is presented in Appendix K.
6.4.1
There was no successful environmental prosecution or
notification of summons received since the Project commencement. The Cumulative Log for environmental summon
and successful prosecution is presented in Appendix K.
7.1.1
The construction
programme for the Project for the next reporting period is presented in Appendix
A.
7.1.2
Works to be undertaken in
the next three months are summarized below:
·
Boulder survey;
·
Open trench for mainlaying
and Mainlaying;
·
Pipe Jacking of trenchless;
·
Hoarding erection and site setup;
·
Trial pit excavation;
·
Formation of piling platform at Zone 1 and Zone 2;
·
Pipe piling for C/C tunnel ELS wall;
·
Civil construction works, e.g.
water supply;
·
Pre-construction condition survey;
·
Site compound site up
·
ELS works in Portion 3; and
·
Canopy table installation in Portion 3.
7.1.3
Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust impact, noise impact, water quality impact, waste
management and landscape and visual.
7.2.1
The key environmental
mitigation measures for the Project in the coming reporting period associated
with above construction activities will include:
Dust
·
Regular
watering to reduce dust emissions from exposed site surface;
·
Stockpile
of dusty materials shall be covered entirely by impervious sheeting;
·
Provide
vehicles washing facilities at all site exits to wash
away any dusty materials from vehicle body;
·
NRMM
Labels should be displayed on the applicable equipment on site by the Contractor;
·
All
vehicle and plant should be cleaned before they leave a construction site.
Noise
·
Only
well-maintained plant should be operated on-site, and plant should be
maintained regularly during the construction programme;
·
Quality
Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water
Quality
·
No
effluent discharge would be allowed before the effluent discharge license is
acquired.
·
Surface
run-off from construction sites should be discharged into dedicated discharge
point via adequately designed sand/ silt removal facilities;
·
Channels/
earth bunds/ sandbags barriers should be provided on site to properly direct
stormwater to silt removal facilities;
·
Silt
removal facilities, channels and manholes should be maintained, and the
deposited silt and grit should be removed regularly;
·
Open
stockpiles of construction materials on sites should be covered with tarpaulin
or similar fabric during rainstorms;
·
Perimeter
channels should be provided on site boundaries where necessary to intercept
stormwater run-off from outside the site so that it will not wash across the
site.
Waste
Management
·
Provision
of sufficient waste disposal points and regular collection of waste;
·
Regular
cleaning and maintenance programme for drainage system;
·
Chemical
containers shall be stored with drip tray underneath;
·
Storage,
handling, transport, and disposal of chemical waste should be arranged in
accordance with the Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes published by EPD, and collected by a licensed chemical waste
collector.
Ecology
·
Minimize
loss of habitats and associated wildlife;
·
Using
directional lighting to prevent excessive light spill into adjacent natural
habitat and disturbance to nocturnal fauna.
Landscape
and Visual
·
Adequate
tree protection measures shall be provided for the trees to be retained on
site.
8.1.1
This is the 3rd
Monthly EM&A Report presents the EM&A works during the reporting period
from 1 June 2023 to 30 June 2023 in accordance with the EM&A Manual.
8.1.2
No Action Level or Limit Level exceedance was
recorded for 1-hour TSP monitoring in the reporting period.
8.1.3
No Action Level or Limit Level exceedance was
recorded for construction noise monitoring in the reporting period.
8.1.4
Environmental site inspections
were conducted on 2, 9, 14, 23 and 30 June 2023 by the ET in the reporting
period.
8.1.5
No environmental complaint was
received in the reporting period.
8.1.6
No notification of summons and
prosecution was received in the reporting period.
8.1.7
The ET will keep track on the
construction works to confirm compliance of environmental requirements and the
proper implementation of all necessary mitigation measures.
8.1.8
No change to the EM&A
programme was made in this reporting period.
8.2.1
The proposed mitigation measures were properly
implemented and were considered effective and efficient in pollution control.
8.2.2
The ET had no recommendation following the
completion of EM&A in the reporting period.